What is the process of construction arbitration?

What's Arbitration (what is the process & definition)

What is the construction arbitration process in the? Arbitration, mediation, litigation. These words are very common in the construction industry. Because the industry is full of disputes.

There are a handful of ways to resolve disputes in the construction industry. But arbitration is the most famous method of resolving contractor and client disputes. In the process of arbitration, Both the parties are agreeing and appointing an independent third party (the arbitrator) to resolve the contractor dispute.

construction arbitration
Image by Mari Ana from Pixabay

Based on the presented evidence and explanations the arbitrator can give a final decision which both parties bonded to accept. Therefore appointed arbitrator should be an expert on the resolving conflicts reasonable way.

Arbitration is very similar to litigation method. Because there are few opportunities to appeal against the decision made by the arbitrator. The main disadvantage of this method is that it can break the relationship between the parties involved.

Appointing of an arbitrator for contractor dispute can happen,

  • The initially agreed agreement (under the contract) by the parties
  • By statue (by government act or law)-Government acts may recommend when and where to resolve disputes using arbitration(The Arbitration Act 1996).
  • By order of the court -Court can order to resolve conflict such as minor claims, by using arbitration

Construction arbitration to resolve contractor dispute- Main characteristics

  1. lesser cost than litigation and arbitrator can decide whom to bear the costs of the process or how to divide the cost of the process,
  2. Because of the arbitrator’s given power he or she can thoroughly make a final decision,
  3. Finality is guaranteed since any of the party has a restricted chance to challenge the decision
  4. Transparency will be there hence arbitrator should point out the reasons for the final decision made,
  5. All the matters and evidence presented will be confidential,
  6. The final decision will be made based on the presented evidence
  7. Since appointed arbitrator is an expert of the selective discipline process will have more pace.

What is Arbitration-Case study for the construction arbitration

John T. Jones Construction Co. v. City of Grand Forks, North Dakota (2003).
Project:- Expansion of the wastewater treatment plant in Grand Forks, ND.
Due to delays on completion of the project City of Grand Forks has recovered liquidity damages of 800$ per day from Jones construction. The contract completion date of the project is November 15, 1999, but the actual completion date of the project is March 20, 2000.
Jones claims that cause of the delay as unanticipated soil condition of the site. And they requested $191,570.59 from the Grand Forks.
After several negotiations both the parties are agreed to follow an arbitration procedure to resolve conflict.

After eight days Arbitrator has given decision with 33 pages of a document stating that Jones is not allowed for any additional reimbursement or time extension under the unanticipated site condition. Right of Grand to recover liquidity damages is confirmed by the arbitrator, Furthermore decision has stated that both the parties to bear own arbitration costs and attorney fees.

Useful links-

  1. CiArb
  2. London Court of International Arb.
  3. Singapore International Arbitration Centre arbitration

(Please comment your thought below, it will help us to improve our articles. If you like this post, please like it)

Check our article What is the Mediation process

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.