Hudson Formula Calculator for EOT Claims OH&P

Hudson formula calculator created by quantitysurveyor.blog team to calculate OH&P. Hudson formula is used to calculate the contractor’s allocated overhead (as per the tender) for the original time frame of the project and damage due to the delay event. (Head Office overheads + profit) ÷ 100 x contract sum ÷ period in (days) x delay … Continue reading Hudson Formula Calculator for EOT Claims OH&P