Image by <a href="https://pixabay.com/users/pixel2013-2364555/?utm_source=link-attribution&utm_medium=referral&utm_campaign=image&utm_content=1745753">S. Hermann & F. Richter</a> from <a href="https://pixabay.com/?utm_source=link-attribution&utm_medium=referral&utm_campaign=image&utm_content=1745753">Pixabay</a>

Contracts

Variations in construction -under FIDIC 1999

By raoneqs

December 24, 2019

Variations in Construction

Variations are also called as change orders in construction. Any modification or change to works (agreed in the contract) is treated as a variation. These modifications or changes can divide into three main categories.

  1. Addition to the work agreed in the contract.
  2. Omission to work agreed in the contract.
  3. Substitution or alteration to work agreed in the contract.

The modern construction industry is developing rapidly day by day. New technologies, materials are introduced every day. Also, the clients are not always satisfied with the first design, and they intend to revise it all the time. Another main reason for change orders is funding problems. Whenever the client realise that they are under budget, they want to alter the design and reduce the cost. So it is inevitable to finish a project with the design agreed at the initial stage.

But importantly, the contractor should agree to change the fundamental nature of the works. Also, the client or consultant cannot omit and reward it to another contractor without the contractor agreeing to it.

FIDIC 1999 Clause 13- Variations and adjustments

Another critical factor is that the change orders in construction cannot issue after the practical completion of the project. According to FIDIC 1999, the engineer(client’s representative) can issue a variation order before issuing Taking-over certificate. And also, the contractor is bound to carry out a variation instructed by the engineer unless the contractor cannot obtain material required to carry out the works. As FIDIC 99 stated, The Contractor should submit a prompt notice with supporting documents so the engineer can cancel or change the variation instructions based on the presented evidence. The contractor cannot change of modified any agreed works as per the contract without engineers approvals and instructions.

Therefore variations in construction might be (as per FIDIC 99),

Value engineering under variations in construction(by contractor)

As per the FIDIC 99 sub-clause 13.2, the contractor can submit a written value engineering proposal at any time to,

Approving and evaluating the value engineering proposal as a variation in construction

If the engineer approves this proposal, the contractor should design this part. And also, any reduction to the contract value will be assessed by the engineer under sub-clause 3.5 (determinations-FIDIC 99) before determining the contractor’s fee. The fee will be half (50%) of the difference of,

But if amount 1 is lesser than the amount 2, the contractor will not be entitled to any fee.

Sub-clause 3.5 – Determinations

The engineer can resolve or determine any matter under sub-clause 3.5 whenever conditions apply accordingly. The engineer will discuss with each party to reach an agreement to the matter. Whenever agreement is not achievable, The Engineer can make a fair determination under the contract. The engineer should provide all particulars to back up the decision made (to all parties). If any of the party not agreeing to the determination made by the engineer can try to revise the decision under clause 20 (FIDIC 99) – claims, disputes & arbitrations). Until that the engineer’s decision will be valid.

What is Variation procedure in the construction industry

Upon the engineer’s instruction to proceed for a variation the contractor can reply in writing stating the reasons not to continue the variation or the contractor can submit,

If the contractor provides a proposal according to sub-clause, 13.2 [value engineering] the engineer can reply with approving, disapproving or commenting. But the contractor cannot delay any work until the engineers respond. The engineer’s responsibility is to evaluate each variation following clause 12 [measurement and evaluation-FIDIC 99]