NEC4 Compensation Events: Notification, Quotation and Assessment Explained

Flat editorial illustration of a quantity surveyor and project manager reviewing a change notice beside a programme chart with a shifted completion milestone, in navy and amber tones
Flat editorial illustration of a quantity surveyor and project manager reviewing a change notice beside a programme chart with a shifted completion milestone, in navy and amber tones

On a JCT job, change is handled through variations, extensions of time and loss and expense – three separate mechanisms with three separate rule books. NEC4 rolls all of that into one process: the compensation event. A compensation event (CE) is any event that, if it happens and isn’t the contractor’s fault, entitles the contractor to have the Prices, the Completion Date and any Key Dates reassessed. Time and money are dealt with together, in one quotation, and ideally agreed before the work is done. That is the theory. In practice, CEs are where most NEC disputes start – usually because someone missed a deadline that the contract treats as final.

This guide walks through the NEC4 Engineering and Construction Contract (ECC) process from a QS’s point of view: what counts as a CE, the notification and quotation timetable, how assessment actually works, and the traps on both sides. If you’re new to the form, our NEC vs JCT vs FIDIC comparison sets out how NEC’s philosophy differs from the other major contract families.

What counts as a compensation event?

The core list sits in clause 60.1 of the NEC4 ECC, which sets out 21 events. A few further events appear in the main and secondary Options, and parties can add bespoke CEs in Contract Data. The ones a QS will see most often are:

  • Changes to the Scope instructed by the Project Manager (60.1(1)) – NEC’s equivalent of a variation.
  • Late access or late provision by the Client – the Client not allowing access to the site by the access date, or not providing something it is required to provide by the date on the Accepted Programme.
  • Late replies – the Project Manager or Supervisor not replying to a communication within the period the contract requires.
  • Physical conditions (60.1(12)) – ground or other physical conditions that an experienced contractor would have judged, at the Contract Date, to have such a small chance of occurring that it would have been unreasonable to allow for them.
  • Weather (60.1(13)) – weather measured in a calendar month that, by comparison with the weather data, occurs on average less often than once in ten years. Only the difference between the actual weather and the 1-in-10-year weather is compensated.
  • Correction of an assumption the Project Manager stated when assessing an earlier CE (60.1(17)).

Notice what is missing: there is no general “catch-all” for delay caused by the client’s other contractors unless it falls within one of the listed events, and contractor-caused problems are never CEs. The contractor carries the risk of anything not listed.

Step 1: notification and the eight-week time bar

Some CEs are notified by the Project Manager – typically those arising from its own instructions or changed decisions. For everything else, the contractor must notify. Under clause 61.3, if the contractor does not notify a CE within eight weeks of becoming aware that the event has happened, the Prices, Completion Date and Key Dates are not changed. That is a genuine time bar: a strong claim notified in week nine can be worth nothing.

There is one important exception. The time bar does not apply to an event the Project Manager should have notified but didn’t. In practice, contractors should not rely on that exception – notify everything, including events you think the PM ought to be notifying. Notifying early costs nothing; notifying late can cost the whole claim.

The Project Manager then has one week (or a longer agreed period) to reply, saying whether the event is a CE and, if so, instructing quotations (clause 61.4). If the PM fails to reply, the contractor can notify that failure; if the PM still hasn’t replied two weeks after that notice, the event is treated as accepted as a CE and the quotation instruction is deemed given. The deeming provision only bites once the contractor has served that second notice, so contractors’ QSs should diarise it.

Step 2: the quotation

Once quotations are instructed, the contractor has three weeks to submit (clause 62.3), unless a longer period is agreed. The quotation must cover both the change to the Prices and any delay to the Completion Date and Key Dates, with details of the assessment and, where the programme is affected, a revised programme showing the effect. The Project Manager has two weeks to respond by accepting it, instructing a revised quotation (with reasons), or notifying that it will make its own assessment.

Silence is, again, dangerous for the PM. If it doesn’t reply in time, the contractor can notify the failure, and if the PM still hasn’t replied within a further two weeks, the quotation is treated as accepted (clause 62.6). Many employer-side QSs have seen a padded quotation become binding this way.

Step 3: how the assessment actually works

This is where NEC is most different from JCT, and where traditional QSs most often go wrong. A compensation event is not valued using bill rates or the activity schedule. Under clause 63.1, the change to the Prices is assessed as the effect of the event on Defined Cost, plus the resulting Fee. Defined Cost is a contractual term, built up from the Schedule of Cost Components (or the Short Schedule for Options A and B) – people, equipment, plant and materials, subcontractors, charges, and so on – and the Fee is a percentage applied to it.

Clause 63.1 also introduces the dividing date. Work done before the dividing date is assessed using actual Defined Cost; work after it is assessed using forecast Defined Cost. For an event arising from a PM instruction or notification, the dividing date is broadly the date of that communication; for other events, it’s the date the contractor notified the event. Because most CEs are quoted before the work is done, the assessment is largely prospective: the contractor prices the risk it carries on the forecast, and if actual cost turns out higher or lower, the assessment is not revisited (clause 66.3). Risk allowances for matters with a significant chance of occurring are included in the forecast.

Rates and lump sums can be used instead of Defined Cost, but only by agreement between the contractor and the Project Manager. Without that agreement, a quotation built from bill rates is not a compliant assessment, however familiar it feels.

For time, clause 63.5 measures the delay to the Completion Date as the amount by which planned Completion is later than planned Completion on the Accepted Programme current at the dividing date. That makes the programme central: if the contractor has no Accepted Programme, the PM can assess CEs on its own view of the programme. Terminal float belongs to the contractor, so a CE that moves planned Completion moves the Completion Date even if the contractor would still have finished early. For more on time-impact methods behind this, see our guide to delay analysis methods.

Early warnings and the 63.7 penalty

NEC4 expects both parties to give early warning of matters that could increase cost, delay completion or impair performance. If the Project Manager notified the contractor, when instructing quotations, that an experienced contractor could have given an early warning but didn’t, the event is assessed as if the warning had been given (clause 63.7). That can reduce the value substantially, because the assessment assumes the cheaper mitigation that an early warning meeting would have found. For contractors, the lesson is simple: raise early warnings freely. The register costs nothing, and a missing warning is one of the PM’s easiest arguments for cutting a quotation.

When the Project Manager assesses

If the contractor doesn’t submit a quotation in time, submits one the PM considers wrong, or fails to show the effect on an Accepted Programme, the PM can make its own assessment (clause 64.1) and must notify that assessment within the time the contract allows. The PM’s failure to assess can, once again, be turned into deemed acceptance of the contractor’s quotation after notice and a further two weeks. PM assessments are a legitimate tool, but they need to be built from Defined Cost and the Accepted Programme like any quotation – an arbitrary figure invites adjudication.

A QS checklist for compensation events

  • Contractor’s QS: keep a CE register with the date of awareness, the notification date and every response deadline. Treat the eight-week bar as absolute.
  • Contractor’s QS: price quotations from Defined Cost and forecast resources, not bill rates, and include programme evidence with every time claim.
  • Contractor’s QS: serve the failure-to-reply notices. Deemed acceptance only works if you trigger it.
  • Employer’s QS / PM: reply to every notification and quotation within the contractual periods. Diarise them as carefully as the contractor does.
  • Employer’s QS / PM: if the contractor missed an early warning, say so when you instruct the quotation, not afterwards.
  • Both: keep the Accepted Programme current. A stale programme turns every CE assessment into an argument.

Handled well, the CE process means change is valued and agreed month by month, so the final account is mostly a formality. Handled badly, it produces a backlog of unassessed events that ends in adjudication. For the official guidance on the procedure, the NEC’s own introduction to compensation events is a good starting point – but always read the executed contract, including any Z clauses, before relying on the standard timescales.