Two-stage tendering and ECI bring the contractor in while the design can still change. Here’s how the two stages work, the JCT PCSA and NEC4 Option X22, the real pros and cons, and how a QS protects value when most of the price is no longer in competition.
Category Archives: Contracts
NEC4 Compensation Events: Notification, Quotation and Assessment Explained
Compensation events are how NEC4 deals with change, delay and cost together. Here’s the notification time bar, the quotation timetable, how Defined Cost and the dividing date drive assessment, and the traps for both contractor and employer QSs.
Direct Loss and Expense Claims Under JCT: How They Differ From an EOT Claim
An extension of time and a loss and expense claim are separate entitlements under JCT, with different trigger events and notice rules. Here’s how the JCT 2024 mechanism works, why FES v HFD makes notice a likely condition precedent, and what a recoverable claim needs.
Practical Completion, Defects Liability and Rectification Periods: What Actually Triggers Each One
Ask three people on a project when the job was “finished” and you’ll often get three dates: the day the client moved in, the day liquidated damages stopped, and the day the last snag was signed off. On most standard forms those don’t share the same trigger. Practical completion, the rectification (or defects liability) period,Continue reading “Practical Completion, Defects Liability and Rectification Periods: What Actually Triggers Each One”
Contractor Insolvency: A QS’s Guide to Step-In Rights, Retention of Title and Keeping a Project Moving
A main contractor going into administration doesn’t end the contract automatically. Here’s how JCT and NEC termination provisions actually work, why retention of title can mean materials on your site still belong to an unpaid supplier, what CIGA 2020’s ipso facto ban means for your subcontractors, and how the Australian position compares.
Collateral Warranties and Third-Party Rights: What QSs Need to Know Before Issuing Them
A funder advancing development finance, a purchaser buying the finished building, and a tenant signing an agreement for lease all have the same problem: none of them has a contract with the contractor, the subcontractors, or the design team who actually built the thing. They sit outside the chain of contracts entirely. If something goesContinue reading “Collateral Warranties and Third-Party Rights: What QSs Need to Know Before Issuing Them”
Payment Notices and Pay Less Notices: Getting the Construction Act Right
What the Construction Act actually requires for payment notices and pay less notices, what happens when neither is served, how JCT and NEC apply the rules, and Australia’s payment schedule equivalent.
Preparing and Agreeing a Final Account: A Step-by-Step QS Guide
What a final account covers, the evidence you need to assemble, JCT/NEC/FIDIC timelines, a step-by-step process for getting one agreed, common pitfalls, and Australia’s AS4000/AS2124 final certificate regime.
Retention in Construction Contracts: Percentages, Release Mechanics and Avoiding Disputes
What retention actually protects, typical percentages and release mechanics under JCT, NEC4 and FIDIC, where retention disputes happen, the UK’s proposed 2026 retention ban, and Australia’s trust account model.
Bonds and Guarantees in Construction Contracts: A Complete Guide
What bonds and guarantees actually protect, the main types of bonds a QS meets on a project, on-demand vs conditional bonds, and how NEC and JCT each deal with them.
